Skip to content

Directional Drilling at Muntons

To facilitate the demolition of the existing Lift shaft/water tower at Muntons Plc, Stowmarket, we were tasked with replacing the current gravity-fed water system with a boosted water supply.
This presented some challenges:

🔎 The new Booster sets are located in an existing pump room, situated approximately 60m from the main building.
📹 The route for the new underground pipework crosses multiple services at varying levels, meaning the whole excavation would require hand digging. The client provided us with a Ground Penetrating Radar survey, which, although it wasn’t 100% accurate, gave us an indication of the location of most of the services.
⛔ The ground conditions are poor, and there are potentially pockets of contamination; the quantity of this is undefined, and as such, the whole dig would need to be treated as contaminated.
⚠️ The location of the new pipe run is within the main entrance to the factory and cannot easily be closed.
✔️ The pipework needed to be 180mm Protecta-Line.
↩️ The route of the new pipework was not a straight line and needed to curve around an existing building.

To mitigate any issues, we decided to explore the option of directional drilling. We called in South East Directional Drilling Services (SEDDS), who rose to the challenge. Two pits were excavated, one at either end of the run to just over 1m in depth, which allowed us to avoid any possible contaminants.

The drill head entered the pit and was drilled to a depth of 2400mm to avoid the deepest service. An operative tracked the drill head using a scanner and guided the driver to ensure the drill was on the correct trajectory. The drill head entered the exit pit in exactly the correct location as predicted.

The drill head was changed to a ‘Reamer’, and the pipe was attached to it. 30 minutes later, the pipe had been drawn through the bored-out hole and was in position, ready for connection to the new supply and chlorinating.

All in all, a very positive experience which saved both Gipping and our client time, money, and inconvenience, vastly reducing the manual labour requirement and leaving any potentially contaminated subsoils safely beneath the reinforced concrete roadway.

The new system will be turned on in the coming weeks, and once proven, will allow the demolition phase to commence.

 

 

News

Work commenced this week on our latest contract award at The Treehouse, East Anglia’s Children’s Hospices (EACH). The breaking ground event was held on Tuesday, after an amazing effort by the Team, led by Gipping Project Manager Chris Crabtree, to get the site ready. The event was blessed by fantastic weather, and as expected, there […]

Read more...

Breaking ground at the Treehouse

Congratulations to Chris Crabtree on his promotion to Project Manager. Chris started his career as a groundworker before progressing to Working Foreman, then Site Manager. Chris joined Gipping over sixteen years ago and is a highly motivated, proactive, well-organised and forward-thinking team member. Chris consistently receives excellent feedback from Clients, notably at our recently completed […]

Read more...

Congratulations, Chris!

It’s not often we can feature two very different projects in the same photograph! Our almost-completed residential project at Hawke Road sits cheek-by-jowl with a recent project win for our Commercial Portfolio Our works at Bauder Flat Roofs’ Headquarters in Landseer Road, Ipswich, comprise the complete refurbishment and extension of the offices, including the replacement […]

Read more...

Project update: Bauder Ltd, Ipswich

The latest Brick Bulletin, by the Brick Development Association, has showcased our project, Amento, which we completed in 2023. Shaun Whiting was Project Manager of the job, with Peter Flatt as Contracts Manager. The article highlights where bold geometric design meets the enduring qualities of clay brick. This project demonstrates how careful material choice delivers […]

Read more...

Amento showcased in the Brick Bulletin

We’ve had a great start to 2026! Not least because we are so proud of Joe Butler, Zac Land, Xena Partridge and Mark Batram, who have all been promoted. Joe has been promoted to Commercial Director and will be responsible for heading up our Commercial Team. This is very much in line with our #EmployeeOwnedTrust […]

Read more...

2026 promotions!

Centre for Mathematical Sciences Our Site Manager, Dale Gregory, has been collecting images to capture the amazing progress at this stunning building within a technically and logistically challenging site. All curved glazing units have now been installed, and internal works are complete, including the installation of a timber framework, new acoustic insulation, and the fabrication […]

Read more...

University of Cambridge PROJECT UPDATE!

What Our Clients Say

  • “Peter was outstanding when it came to communications and implementing changes and fixes that were required by the building work supplier. Very happy to recommend Gipping's services to others.”

    Oliver Squirrell, Old Jet Airspace Programme

  • “I just wanted to thank you again for pretty much everything! I absolutely love our home and it was totally worth the wait. There isn’t a single thing I’d change, it really is perfect. The landscapers have been now too and it’s totally transformed the outside space, it just looks incredible. I feel super lucky to live here, every time I pull up back home I smile and feel so grateful and lucky.  All the workmen have been incredibly lovely and gone above and beyond too, you have such a great team of people, they are extremely lovely and that makes a huge difference. I wish you well in all that you do creating beautiful homes for people. Thank you so so much.”

    Kayleigh Williams: Wix

  • “As a team, Gipping met every expectation throughout the project. Steve James provided the exact role and attitude required for a project of this nature. The way he managed the works on site, given the difficult “live” environment was a credit to the firm. The overall management and support for Steve from Steve Offord and Joe was also a large factor in the smooth running of the scheme. All involved should be commended and are a credit to Gipping. Thank you for your part in a very successful scheme.”

    Ben Mitchell, The Design partnership: Walden Place

  • “Carl, and the team, were fantastic during this phase of the project. Carl kept us updated with how the work was going and always had time to check with us if he thought things would impact on the running of the school. The site was always clean and tidy. The project was delivered slightly ahead of schedule, which made the transition into the build much easier for us! Thank you!”

    Hannah Brookman, Tollgate Primary School Phase I

  • “It was a pleasure working with Gipping and we are very happy with our new home. Shaun Whiting was an exceptional Site Manager and remained professional, approachable and friendly throughout the entire build. The site was always tidy, well-managed and busy. We felt as if the entire Gipping team took our project seriously and truly cared about getting the build right. I would highly recommend you to anyone who is considering building a home.”

    Elizabeth Goodrich, Amento