From foundations to first floors…..freshly picked footage of progress at Ravenswood.
Video and images show the site from the top of Block 1 where the trusses are now in situ with roof coverings to commence imminently.
The bungalows are water-tight with solar PV panels added while first floor joists are being added to blocks 5 – 8.
Works are all on programme with first handover scheduled for Summer 2024