Carlton Colville Veterinary Practice, Lowestoft

Designed to create a modern, purpose-built healthcare facility, the project includes a steel-frame structure, striking zinc roofing, aluminium glazing systems, high-quality brickwork and render finishes, together with an external works package.

Positioned at the heart of a busy local centre, adjacent to retail, healthcare and residential areas, careful planning and coordination ensured construction progressed safely while minimising impact on the local community.

The project comprised the design and construction of a new single-storey shell and core building for a veterinary practice at Carlton Colville Local Centre, Ashburnham Way, Lowestoft.

The works included the steel frame, zinc roof coverings, aluminium curtain walling, windows and doors, brick and render façades, drainage, service infrastructure, landscaping and external works. The veterinary fit-out and specialist installations formed a separate tenant package.

  • Sector: Commercial and Industrial
  • Client: Rookman Properties Ltd (LCP)
  • Employer’s Agent/Contract Administrator: Bidwells
  • Architect: Ingleton Wood
  • Structural Engineer: Ingleton Wood
  • Commenced: February 2026
  • Practical Completion: September 2026
  • Procurement Method: Design and Build
  • Value at completion: £1,000,000

Challenges and Constraints

The site sits beside an operating supermarket, medical centre and residential properties, requiring careful planning of deliveries, lifting operations and the public interface. Coordination of below-ground drainage, steel erection and incoming utility connections was a key consideration, alongside the interface with the tenant’s separate fit-out.

Construction Processes and Methods

Groundworks and below-ground drainage were followed by erection of the structural steel frame, roof deck and zinc roof coverings. Brickwork, rendered façades and aluminium glazing formed the building envelope. External works included drainage attenuation, hardstanding, parking, footpaths and landscaping, with service connections coordinated for the subsequent tenant fit-out.

Programme

The programme linked drainage and groundworks with steel erection, roofing, façade installation and external works. Drainage revisions and utility-provider dates required ongoing coordination. The final contract duration and certified practical completion date are to be confirmed.

Environmental

As responsible contractors who are ISO14001 accredited, we completed environmental risk assessments, minimised waste and any waste was disposed of using licensed companies. Waste was sorted at the collection depot. Typically, 90% of waste is recycled.

The scheme included surface-water drainage and attenuation. The supply register identifies recycled sand from Silverton Aggregates in Great Yarmouth. Energy compliance and EPC requirements needed coordination with the separate tenant fit-out; PV was not included in Gipping’s final scope.

Social Value

80% of the supply chain was local.

Pallets were given to locals for reuse

Carlton Colville Veterinary Practice

What Our Clients Say

“
  • “Peter was outstanding when it came to communications and implementing changes and fixes that were required by the building work supplier. Very happy to recommend Gipping's services to others.”

    Oliver Squirrell, Old Jet Airspace Programme

  • “I just wanted to thank you again for pretty much everything! I absolutely love our home and it was totally worth the wait. There isn’t a single thing I’d change, it really is perfect. The landscapers have been now too and it’s totally transformed the outside space, it just looks incredible. I feel super lucky to live here, every time I pull up back home I smile and feel so grateful and lucky.  All the workmen have been incredibly lovely and gone above and beyond too, you have such a great team of people, they are extremely lovely and that makes a huge difference. I wish you well in all that you do creating beautiful homes for people. Thank you so so much.”

    Kayleigh Williams: Wix

  • “As a team, Gipping met every expectation throughout the project. Steve James provided the exact role and attitude required for a project of this nature. The way he managed the works on site, given the difficult “live” environment was a credit to the firm. The overall management and support for Steve from Steve Offord and Joe was also a large factor in the smooth running of the scheme. All involved should be commended and are a credit to Gipping. Thank you for your part in a very successful scheme.”

    Ben Mitchell, The Design partnership: Walden Place

  • “Carl, and the team, were fantastic during this phase of the project. Carl kept us updated with how the work was going and always had time to check with us if he thought things would impact on the running of the school. The site was always clean and tidy. The project was delivered slightly ahead of schedule, which made the transition into the build much easier for us! Thank you!”

    Hannah Brookman, Tollgate Primary School Phase I

  • “It was a pleasure working with Gipping and we are very happy with our new home. Shaun Whiting was an exceptional Site Manager and remained professional, approachable and friendly throughout the entire build. The site was always tidy, well-managed and busy. We felt as if the entire Gipping team took our project seriously and truly cared about getting the build right. I would highly recommend you to anyone who is considering building a home.”

    Elizabeth Goodrich, Amento