Drovers House, Bury St Edmunds, Suffolk

Full internal refurbishment of the existing office building including lift installation, heating and ventilation, partitioning, finishes and fixtures and fittings on behalf of Allied Health.

Works were carried out in three phases to allow the Employer to continue occupation during the construction.

The alteration works included the removal of suspended ceilings, construction of timber stud partitions to form four rooms, providing doors, repositioning of light fittings and supplying new wash hand basin.

We formed a lift shaft and pit including removing a section of brickwork and an aluminium window to create access into the working area.

We carried out alteration works to the first floor to create six new treatment rooms, a group room, a waiting area and a lift lobby.

This included M&E amendments and fitting new male toilet facilities. The enabling work for the new facilities required external drainage to be installed back to an existing foul drain run.

Alteration works to the ground floor comprised three new treatment rooms, an office/meeting room, a gym, staff room, comms room and reception area. Works included the removal of temporary partitions installed in Phase One.

  • Sector: Health and Care
  • Location: Bury St Edmunds, Suffolk
  • Client: Allied Health Professionals Suffolk
  • Employer‘s Agent/Architect: Bennetts (SA) LLP
  • Commenced: March 2016
  • Completed: October 2016
  • Procurement Method: Single Stage Drawings and Spec.
  • Contract Value: £315,000

“All of Gipping’s employees were very courteous and helpful whenever I visited the site. In particular, Shaun Whiting, who responded quickly to any queries or requests I had, and was always willing to assist on site or over email.”

Lynn Lay Allied Health Professionals

Challenges and Constraints

  • Working safely and efficiently within a live healthcare environment without causing disruption.
  • Discovery of unforeseen asbestos.
  • Sewer Connection to highway – confined space
  • Adjoining neighbours / existing residents
  • Live services.
  • Pedestrian traffic across site entrance.

Construction Processes and Methods

We formed temporary access using scaffold staircase to gain access to the first floor (avoiding disruption to the Client’s physio therapy business which remained operational throughout the works)

A new passenger lift formed part of the works which involved construction of new lift pit and shaft. At ground floor level we constructed temporary screening. A section of the first floor was trimmed and removed to enable the lift installation.

At first floor, the existing partitioning and raised access floor and other finishes were stripped out with new partitions, flooring, ceilings, MEP, fixtures and fittings to create new therapy rooms, offices and ancillary rooms

Externally works comprised new drainage, access path and new draft lobby.

Environmental

As responsible contractors who are ISO14001 accredited, we completed environmental risk assessments, minimised waste and any waste was disposed of using licensed companies. Waste was sorted at the collection depot. Typically, 90% of waste is recycled.

 

Drovers House Drovers House Drovers House

What Our Clients Say

  • “Peter was outstanding when it came to communications and implementing changes and fixes that were required by the building work supplier. Very happy to recommend Gipping's services to others.”

    Oliver Squirrell, Old Jet Airspace Programme

  • “I just wanted to thank you again for pretty much everything! I absolutely love our home and it was totally worth the wait. There isn’t a single thing I’d change, it really is perfect. The landscapers have been now too and it’s totally transformed the outside space, it just looks incredible. I feel super lucky to live here, every time I pull up back home I smile and feel so grateful and lucky.  All the workmen have been incredibly lovely and gone above and beyond too, you have such a great team of people, they are extremely lovely and that makes a huge difference. I wish you well in all that you do creating beautiful homes for people. Thank you so so much.”

    Kayleigh Williams: Wix

  • “As a team, Gipping met every expectation throughout the project. Steve James provided the exact role and attitude required for a project of this nature. The way he managed the works on site, given the difficult “live” environment was a credit to the firm. The overall management and support for Steve from Steve Offord and Joe was also a large factor in the smooth running of the scheme. All involved should be commended and are a credit to Gipping. Thank you for your part in a very successful scheme.”

    Ben Mitchell, The Design partnership: Walden Place

  • “Carl, and the team, were fantastic during this phase of the project. Carl kept us updated with how the work was going and always had time to check with us if he thought things would impact on the running of the school. The site was always clean and tidy. The project was delivered slightly ahead of schedule, which made the transition into the build much easier for us! Thank you!”

    Hannah Brookman, Tollgate Primary School Phase I

  • “It was a pleasure working with Gipping and we are very happy with our new home. Shaun Whiting was an exceptional Site Manager and remained professional, approachable and friendly throughout the entire build. The site was always tidy, well-managed and busy. We felt as if the entire Gipping team took our project seriously and truly cared about getting the build right. I would highly recommend you to anyone who is considering building a home.”

    Elizabeth Goodrich, Amento