Works to Thetford Healthy Living Centre were completed in two phases. Phase One involved refurbishment and reconfiguration of office space to consulting rooms, treatment rooms, utility rooms and stores. Phase two saw the creation of a reception and waiting area. A new external lift shaft increased usability options for the first floor. Parking capacity was doubled and EV points installed.

Works included full strip-out of ceilings, floor finishes, studwork partitions and redundant mechanical and electrical services.

Extreme care and co-operation were imperative as ground floor and unaffected first floor areas were fully operational including dentistry, podiatry, phlebotomy, eye clinics, minor operations and two GP surgeries. Noise and cleanliness were critically monitored at all times.

Car park, lift shaft and drainage works were carried out in live areas so segregation of works, banking of vehicles and assisting with visitors, public and patients were of paramount importance. Re-surfacing and extension of the existing car park over doubled its capacity along with the installation of two EV charging points.

Out of hours works minimised disruption, ensuring all areas were kept working at all times.

Daily dialogue with the building management of the Healthy Living Centre maintained a good flow of information.

  • Sector: Health & Care
  • Location: Thetford, Norfolk
  • Client: Norlife Ltd
  • Employer‘s Agent/Architect: Chaplin Farrant Ltd
  • Structural Engineer: Canham Consulting
  • Commenced: August 2023
  • Completed: April 2024
  • Procurement Method: Single Stage Drawings and Spec.
  • Contract Value: £1,500,000

Challenges and Constraints

  • Working safely and efficiently within a live healthcare environment without causing disruption.
  • Segregation of works, banking of vehicles and assisting with visitors, public and patients were of paramount importance.
  • Live services.
  • Pedestrian traffic.

Construction Processes and Methods

A new external passenger lift formed part of the works which involved construction of new lift pit and shaft.

At first floor level we constructed temporary screening.

The existing partitioning and other finishes were stripped out with new partitions, flooring, ceilings, MEP, fixtures and fittings to create new therapy rooms, offices and ancillary rooms on the first floor.

Externally works comprised new drainage, re-surfacing and extension of the existing car park along with the installation of two EV charging points.

Environmental

As responsible contractors who are ISO14001 accredited, we completed environmental risk assessments, minimised waste and any waste was disposed of using licensed companies. Waste was sorted at the collection depot. Typically, 90% of waste is recycled.

 

Thetford Healthy Living Centre

What Our Clients Say

  • “Peter was outstanding when it came to communications and implementing changes and fixes that were required by the building work supplier. Very happy to recommend Gipping's services to others.”

    Oliver Squirrell, Old Jet Airspace Programme

  • “I just wanted to thank you again for pretty much everything! I absolutely love our home and it was totally worth the wait. There isn’t a single thing I’d change, it really is perfect. The landscapers have been now too and it’s totally transformed the outside space, it just looks incredible. I feel super lucky to live here, every time I pull up back home I smile and feel so grateful and lucky.  All the workmen have been incredibly lovely and gone above and beyond too, you have such a great team of people, they are extremely lovely and that makes a huge difference. I wish you well in all that you do creating beautiful homes for people. Thank you so so much.”

    Kayleigh Williams: Wix

  • “As a team, Gipping met every expectation throughout the project. Steve James provided the exact role and attitude required for a project of this nature. The way he managed the works on site, given the difficult “live” environment was a credit to the firm. The overall management and support for Steve from Steve Offord and Joe was also a large factor in the smooth running of the scheme. All involved should be commended and are a credit to Gipping. Thank you for your part in a very successful scheme.”

    Ben Mitchell, The Design partnership: Walden Place

  • “Carl, and the team, were fantastic during this phase of the project. Carl kept us updated with how the work was going and always had time to check with us if he thought things would impact on the running of the school. The site was always clean and tidy. The project was delivered slightly ahead of schedule, which made the transition into the build much easier for us! Thank you!”

    Hannah Brookman, Tollgate Primary School Phase I

  • “It was a pleasure working with Gipping and we are very happy with our new home. Shaun Whiting was an exceptional Site Manager and remained professional, approachable and friendly throughout the entire build. The site was always tidy, well-managed and busy. We felt as if the entire Gipping team took our project seriously and truly cared about getting the build right. I would highly recommend you to anyone who is considering building a home.”

    Elizabeth Goodrich, Amento