Challenges and Constraints
The project was undertaken within and alongside an existing church building in a residential area, with restricted access and limited space for deliveries, storage and site set-up. The age and construction of the existing building meant that opening-up works revealed unforeseen conditions, including rotten structural timbers and the need for additional temporary works, structural input and steelwork modifications.
A key challenge was the front elevation, where the existing structure had to be supported and altered in a carefully controlled sequence. The curtain walling and feature cross also required detailed coordination before fabrication and installation, as these elements were critical to closing up the extension and releasing internal finishes. Existing asbestos-containing materials were identified, managed and retained in place where appropriate in accordance with the asbestos management information.
Construction Processes and Methods
The works combined traditional refurbishment with a new two-storey extension. Construction included groundworks and drainage, masonry, structural steelwork, engineered timber and timber connections, roof construction, curtain walling, windows, a new staircase and lift, internal partitions, dry lining, carpentry, fire stopping and new mechanical and electrical installations.
Temporary works and a staged structural sequence were developed for alterations to the existing front elevation. Specialist-designed packages included the temporary works, engineered timber, curtain walling, architectural metalwork, staircase and mechanical and electrical services. Close coordination between the design team, structural engineer and specialist subcontractors was needed to resolve interfaces with the existing building.
Programme
The works commenced on 2 June 2025. The programme required the new extension and refurbishment works to progress alongside one another, with several specialist trades coordinated across the available work fronts.
The programme was affected by unforeseen conditions uncovered within the existing building, including rotten structural elements, additional temporary works and redesign, together with the time needed to finalise the curtain walling and feature cross details. These matters affected the critical path because the extension could not be fully closed up until the external envelope was resolved. To maintain momentum, labour and sequencing were regularly reviewed, multiple trades worked concurrently, and second-fix and finishing works were progressed in every area available. Completion date: to be confirmed.
Environmental
Site waste was segregated and removed through licensed waste carriers, with materials recycled where practicable. Deliveries and material storage were coordinated to suit the constrained site and reduce unnecessary vehicle movements. Existing parts of the building were retained and refurbished rather than replaced, extending the life of the structure and reducing the amount of new material required.
Social Value
The project improves the accessibility and long-term usability of an established community church. The new lift, staircase and upgraded facilities will allow the building to serve a wider range of users and support the church’s ongoing community activities. Regular liaison was maintained with the client and church representatives throughout the works, with progress meetings and site visits used to coordinate decisions and keep stakeholders informed.