Construction of ten starter homes in Jaywick, Essex with associated external works on brownfield site. Timber framed construction for the living space constructed on masonry ground floor garages (to mitigate flood risk).

Starter homes, Jaywick, Essex
- Sector: Residential
- Location: Jaywick, Essex
- Client Tendring District Council
- Contract Administrator/ Architect: Tendring District Council
- Structural Engineer: Richard Jackson Consulting
- Commenced: May 2019
- Completed: October 2020
- Procurement Method: Single Stage Tender
- Contract Value: £2,100,000
Challenges and Constraints
The scheme was coastal, and within a designated flood plain. The ground conditions and weather made for challenging times, especially as the timber frame was programmed to be constructed in winter months. This made craneage hard. Works had to be planned accordingly.
Construction Processes and Methods
Dwellings built to Flood risk design, with piled foundations, with masonry garages to the ground floor, with timber frames contemporary style dwellings above. Permeable paving parking areas and landscaped rear gardens.
Environmental
As responsible contractors who are ISO14001 accredited, we completed environmental risk assessments, minimised waste and any waste was disposed of using licensed companies. Waste was sorted at the collection depot. Typically, 90% of waste is recycled.