Wells Hall Primary School, Suffolk

Extension and alterations to provide additional hall space, new WC facilities, additional group space and improved access at Wells Hall Primary School. Works were completed in three phases to enable the school to remain operational during construction.

  • SECTOR: Education
  • Location: Sudbury, Suffolk
  • CLIENT: Wells Hall Primary School
  • ARCHITECT: PCH Associates Ltd
  • Structural Engineer: Pure Structures
  • COMMENCED: August 2021
  • COMPLETED: September 2022 (in three phases)
  • PROCUREMENT METHOD: Two stage Tender
  • CONTRACT VALUE: £1,500,000

Challenges and Constraints

Working safely and efficiently within an education environment without causing disruption to the school. Large volume of work required to enable the school to open after the Summer holidays.

Construction Processes and Methods

The new build extension was a steel frame with SFS infill. The facade of the building was clad with Rockpanel and the roof was a Bauder system. Large areas of the project involved refurbishment works. The school had a history of flooding so there was a large soakaway and new surface water drainage installed to mitigate the flooding.

Environmental

As responsible contractors who are ISO14001 accredited, we completed environmental risk assessments, minimised waste and any waste was disposed of using licensed companies. Waste was sorted at the collection depot. Typically, 90% of waste is recycled.

Wells Hall Primary School Wells Hall Primary School

What Our Clients Say

  • “Peter was outstanding when it came to communications and implementing changes and fixes that were required by the building work supplier. Very happy to recommend Gipping's services to others.”

    Oliver Squirrell, Old Jet Airspace Programme

  • “I just wanted to thank you again for pretty much everything! I absolutely love our home and it was totally worth the wait. There isn’t a single thing I’d change, it really is perfect. The landscapers have been now too and it’s totally transformed the outside space, it just looks incredible. I feel super lucky to live here, every time I pull up back home I smile and feel so grateful and lucky.  All the workmen have been incredibly lovely and gone above and beyond too, you have such a great team of people, they are extremely lovely and that makes a huge difference. I wish you well in all that you do creating beautiful homes for people. Thank you so so much.”

    Kayleigh Williams: Wix

  • “As a team, Gipping met every expectation throughout the project. Steve James provided the exact role and attitude required for a project of this nature. The way he managed the works on site, given the difficult “live” environment was a credit to the firm. The overall management and support for Steve from Steve Offord and Joe was also a large factor in the smooth running of the scheme. All involved should be commended and are a credit to Gipping. Thank you for your part in a very successful scheme.”

    Ben Mitchell, The Design partnership: Walden Place

  • “Carl, and the team, were fantastic during this phase of the project. Carl kept us updated with how the work was going and always had time to check with us if he thought things would impact on the running of the school. The site was always clean and tidy. The project was delivered slightly ahead of schedule, which made the transition into the build much easier for us! Thank you!”

    Hannah Brookman, Tollgate Primary School Phase I

  • “It was a pleasure working with Gipping and we are very happy with our new home. Shaun Whiting was an exceptional Site Manager and remained professional, approachable and friendly throughout the entire build. The site was always tidy, well-managed and busy. We felt as if the entire Gipping team took our project seriously and truly cared about getting the build right. I would highly recommend you to anyone who is considering building a home.”

    Elizabeth Goodrich, Amento