New build car workshops and valet at ground floor with offices and storage at first floor, constructed in two phases. Phase One, a car workshop area and shell, was completed in just 26 weeks. Phase Two comprised fit-out of offices which was completed three months later.
Construction comprised stone piles to stabilise the ground, rc raft, steel frame, SFS wall with sheet wall and roof cladding, aluminium glazing with solar shading. Internally, three staircases and a lift to provide access to the first floor were fitted out for the offices.

Westdrive, Skyline 120 Braintree, Essex
- Sector: Commercial and Industrial
- Location: Braintree, Essex
- Client: Westdrive (Colchester) Ltd
- Contract Administrator: Hoggarth Cooke Partnership
- Architect: Emptage Architects
- Structural Engineers: David Burton Sweetlove
- Commenced: March 2018
- Completed: February 2019
- Procurement Method: Single Stage Tender
- Contract Value: £3,000,000
Challenges and Constraints
The site was constricted with deep drainage at its entrance. There was also a large surface water attenuation tank which took up a large surface area of the site whilst being installed. The project included the installation of hydraulic lifting platforms for the service bays. These had to be installed 2.5m below the floor slab with millimetre precision. Given the nature of the building, the M&E services had to be carefully co-ordinated.
Construction Processes and Methods
Vibro piles due to poor ground conditions.
Steel frame building with composite and built up cladding system.
Power floated ground floor slab with pre-cast planks forming upper floors.
The yard was a mixture of permeable paving, concrete and asphalt.
Programme
The project was completed in two phases and both were completed on time.
Phase 1: Workshop and valeting bays
Phase 2: Upper floor offices.
Environmental
Surface water.
As responsible contractors who are ISO14001 accredited, we completed environmental risk assessments, minimised waste and any waste was disposed of using licensed companies. Waste was sorted at the collection depot. Typically, 90% of waste is recycled.



